Scope

     Winninger Excavating, Inc. performed the mass earthwork and site utilities for a 70-acre trucking facility. At the bidding stage Winninger Excavating, Inc. helped the client balance the site by suggesting grading changes which drastically saved cost. Over 10,000 linear-feet of watermain including an auger and casing under State Route 30 was installed for this project.

     This project had a large amount of storm sewer required, as well as a sanitary lift station. Despite rain making over 40 days unworkable, Winninger Excavating, Inc. was able to turn this site over for paving stone on schedule.

Location

     Matteson, IL

Client

     Coast Construction Group

Project Start

     Fall 2021